Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.36 | 0 | 0 |
61W13 :
Administrative Approval Detail : भारत सरकार के पत्र संख्या RO/UK/12014/83/Annual Plan/2019-20, Dt. 30-03-2020जाॅब संख्या NH-87Ext.(109)-Ur-2019-20-566
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
495.27
Resanction Cost :
495.27
Tentative Cost :
495.27
Exp. Upto Last Fy : 250.31
For CFY 2024-2025
Remaining : 244.96
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 250.31
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
4 years 3 months ago
30 Mar 2020
Tentative Completion date:
3 years 1 month ago
15 Jun 2021
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck:
Work Completed -- as on 19-Jul-2021
Physical Peramenters