Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.43 | 0 | 0 |
61W14 :
Administrative Approval Detail : भारत सरकार के पत्र संख्या RO/UK/Annual Plan/2020-21/Haldwani/06, Dt. 05-03-2021जाॅब संख्या NH-121 (309)-UR-2020-21-587
TS Amount (lakhs) : 351.99 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
351.99
Resanction Cost :
351.99
Tentative Cost :
351.99
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 351.99
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Construction Started
Physical Progress:
At start of FY 2024-2025 : 4 %
Up to Date : 4 %
Sanction on :
3 years 4 months ago
05 Mar 2021
Tentative Completion date:
2 years 6 months ago
20 Dec 2021
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck:
Construction of Jersey Barrier work in progress. -- as on 16-Aug-2021