Work Profile Report [61W17]

राष्ट्रीय मार्ग संख्या 121 (नया 309) के कि0मी0 28.00 (रामनगर) से कि0मी0 63.00 (मरचूला) में आई0आर0क्यू0पी0 कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan

  • Components
  • Forest
  • Remarks

    Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : File No RO/UK/ Annual Plan /2021-22/ Haldwani/ 01 dt.23.11.2021 Job No.NH-121 (New No 309)/-UK-2021-22-599

TS Amount (lakhs) : 2425.52 Lacs

Budget Financial Head : Deposit ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

2425.94

Resanction Cost :

2425.94

Tentative Cost :

2425.94

Exp. Upto Last Fy :

0.00

For CFY 2025-2026

Remaining :

2,425.94

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.00

Work completed

Sanction on : 3 years 6 months ago

23 Nov 2021

Physical Progress:

At start of FY 2025-2026 :

100 %

Up to Date :

100 %

Tentative Completion date on : 1 year 9 months ago

02 Aug 2023

Actual Completion Date : 1 year 10 months ago

24 Jul 2023

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
33.12
33.12
33.12
-

Remark

view all

Work Completed -- as on 11-Oct-2024

Rating : 100

Forest Case Pending At : 00: Not Started

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand