Work Profile Report [61W4]
Fin Plan
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : भारत सरकार के पत्र संख्या Uttarakhand(1)/2016-S&R (B) Dt. 20-03-2017जाॅब संख्या 121/Uttarakhand(1)/16-S&R(B)-007
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
7652.00
Resanction Cost :
5689.00
Tentative Cost :
5689.00
Exp. Upto Last Fy :
699.78
For CFY 2024-2025
Remaining :
4,989.22
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
699.78
Construction Started
Sanction on : 7 years 9 months ago
20 Mar 2017
Physical Progress:
At start of FY 2024-2025 :
16 %
Up to Date :
65 %
Tentative Completion date on : 3 months 3 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Out of 22 no. foundation 6 are completed. Out of 32 no. substructure 8 are completed. Out of 1711 RM drain 1078 RM completed. Due to delay in CALA appointment still about 3% land has not been transferred to Contractor. -- as on 17-Aug-2021
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1 Road 2 Road 3 Road 4
Bridges on The Basis of AI: Feeder canal
© PWD Uttarakhand