Work Profile Report [61W5]
Fin Plan
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : भारत सरकार के पत्र संख्या RO/UK/12014/62/2018-Annual Plan, Dt. 01-03-2019जाॅब संख्या NH-87 Ext.-UK-2018-19-04 (RO)
TS Amount (lakhs) : 462.69 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
462.69
Resanction Cost :
462.69
Tentative Cost :
462.69
Exp. Upto Last Fy :
285.81
For CFY 2024-2025
Remaining :
176.88
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
285.81
Work completed
Sanction on : 5 years 8 months ago
01 Mar 2019
Physical Progress:
At start of FY 2024-2025 :
85 %
Up to Date :
100 %
Tentative Completion date on : 3 years 3 weeks ago
31 Oct 2021
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Foundation, Substructure and site erection work completed. Shuttering for deck slab in progress. Project is delayed due to covid 19 Ist and IInd wave -- as on 17-Aug-2021