Administrative Approval Detail : RO/UK/AP2023-24/NH-134/Barkot/Landslide (Computer No. 229398) -job no -RO/UK/AP/NH-134/2023-24/679
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
8027.39
Resanction Cost :
8027.39
Tentative Cost :
8027.39
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
8,027.39
Demand :
2,386.00
Allotment :
1,393.33
Exp in CFY :
1,393.33
Total Up to Date Exp :
1,393.33
Construction Started
Sanction on : 1 year 6 months ago
30 Jan 2024
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
61 %
Tentative Completion date on : 8 months 3 weeks from now
30 Apr 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
physical progress-61.14 % Work in progress. -- as on 29-Jul-2025