Work Profile Report [62W6]

Rehabilitation and ugradation to 2-lane with paved shoulder configuration from existing km 172.90 to km 194.150 (desigh Ch. 49.30 to 70.30)of NH-94 in the state of Uttarakhand on EPC mode under improvement to NH connectivity to Chardham.
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : आर0ओ0-यू0के0-12014-01-2017-चारधाम-ऐ0पी0job no. NH-134(Old no. 94)-UR-2017-18-517

TS Amount (lakhs) : 29368 Lacs

Budget Financial Head : SRMD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

29368.00

Resanction Cost :

29368.00

Tentative Cost :

29368.00

Exp. Upto Last Fy :

23,247.86

For CFY 2024-2025

Remaining :

6,120.14

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

23,247.86

Construction Started

Sanction on : 6 years 10 months ago

19 Feb 2018

Physical Progress:

At start of FY 2024-2025 :

100 %

Up to Date :

100 %

Tentative Completion date on : 1 year 8 months ago

19 Apr 2023

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
21
21
21
-

Remark

view all

physical progress-100 %
financial progress -97.32 %
-- as on 05-Sep-2023

Rating : 100

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Roads on The Basis of AI: Road 1 Road 2

Bridges on The Basis of AI: Chamrota Bridge