Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 75.406 | 75.406 | 75.000 | 0.40600000000001 | 0.406 | 0.406 |
Jobs | 1 | 1 | 0 | 1 | 0 | 0 |
63W1 :
Administrative Approval Detail : शासनदेश संख्या 295 /III (3)/2020 -21 सी० आर० एफ० /2019 लो० नि० वि० अनुभाग-3 देहरादून दिनांक 17 फ़रवरी 2020
TS Amount (lakhs) : 2437.32 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
2437.32
Resanction Cost :
2437.32
Tentative Cost :
2437.32
Exp. Upto Last Fy : 2,252.72
For CFY 2024-2025
Remaining : 184.60
Demand : 40.00
Allotment : 20.00
Exp in CFY : 15.56
Total Up to Date Exp : 2,268.28
Construction Started
Physical Progress:
At start of FY 2024-2025 : 94 %
Up to Date : 100 %
Sanction on :
4 years 5 months ago
17 Feb 2020
Tentative Completion date:
2 months 1 week from now
30 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
Work Completed. Minor Rectification works is in progress. -- as on 10-Jul-2024