Work Profile Report [63W1]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनदेश संख्या 295 /III (3)/2020 -21 सी० आर० एफ० /2019 लो० नि० वि० अनुभाग-3 देहरादून दिनांक 17 फ़रवरी 2020
TS Amount (lakhs) : 2437.32 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
2437.32
Resanction Cost :
2437.32
Tentative Cost :
2300.00
Saving
137.32
Exp. Upto Last Fy :
2,346.63
For CFY 2025-2026
Remaining :
90.69
Demand :
0.00
Allotment :
93.91
Exp in CFY :
0.00
Total Up to Date Exp :
2,346.63
Work completed
Sanction on : 5 years 2 months ago
17 Feb 2020
Physical Progress:
At start of FY 2025-2026 :
94 %
Up to Date :
100 %
Tentative Completion date on : 9 months 2 weeks ago
30 Jun 2024
Actual Completion Date : 9 months 2 weeks ago
30 Jun 2024
Physical Linear Components
Remark
Work Completed. -- as on 11-Nov-2024