Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 56.115 | 56.115 | 45.000 | 11.115 | 11.115 | 8.000 |
63W15 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : File No. RO/UK/Annual Plan/2021-22/Dhumakot-03 Dated 22nd November, 2021(Job No:- NH-121(New No. 309)/UK/2021-22-598)
TS Amount (lakhs) : 4930.15 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
4930.15
Resanction Cost :
4930.15
Tentative Cost :
4930.15
Exp. Upto Last Fy : 2,198.24
For CFY 2024-2025
Remaining : 2,731.91
Demand : 1,005.34
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 2,198.24
Construction Started
Physical Progress:
At start of FY 2024-2025 : 66 %
Up to Date : 80 %
Sanction on :
2 years 7 months ago
22 Nov 2021
Tentative Completion date:
3 months 1 week from now
25 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
Work in Progress -- as on 08-Jan-2023
Physical Peramenters