Work Profile Report [63W15]
Remarks
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : File No. RO/UK/Annual Plan/2021-22/Dhumakot-03 Dated 22nd November, 2021(Job No:- NH-121(New No. 309)/UK/2021-22-598)
TS Amount (lakhs) : 4930.15 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
4930.15
Resanction Cost :
4930.15
Tentative Cost :
4930.15
Exp. Upto Last Fy :
2,198.24
For CFY 2024-2025
Remaining :
2,731.91
Demand :
1,005.34
Allotment :
0.00
Exp in CFY :
398.02
Total Up to Date Exp :
2,596.26
Construction Started
Sanction on : 3 years 1 day ago
22 Nov 2021
Physical Progress:
At start of FY 2024-2025 :
66 %
Up to Date :
80 %
Tentative Completion date on : 4 weeks 1 day ago
25 Oct 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Work in Progress -- as on 08-Jan-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand