Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 8 | 8 | 0 | ||
Jobs | 1 | 1 | 1 | 0 |
Closed Work 63W6 :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: Shankerpur Bridge
Administrative Approval Detail : फा० सं० आर०ओ०/यू०के०/12014 /49 /2018/एन्यूवल प्लान, दिनांक 6 मार्च 2019
TS Amount (lakhs) : 1054.26 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
1054.26
Resanction Cost :
1054.26
Tentative Cost :
1054.26
Exp. Upto Last Fy : 680.85
For CFY 2024-2025
Remaining : 373.41
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 680.85
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
5 years 4 months ago
06 Mar 2019
Tentative Completion date:
2 years 11 months ago
15 Aug 2021
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck:
Work in Completed -- as on 17-Aug-2021
Physical Peramenters