Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 10 | 10 | 0.000 | 10 | 0.000 | 0.000 |
67W307 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 5490/।।।घ्2घ्/13-27घ्प्रा0आ0घ्/2013 दि0 17-10-2013
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
92.70
Resanction Cost :
92.70
Tentative Cost :
92.70
Exp. Upto Last Fy : 42.67
For CFY 2024-2025
Remaining : 50.03
Demand : 2.00
Allotment : 0.00
Exp in CFY : 3.13
Total Up to Date Exp : 45.80
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 40 %
Sanction on :
10 years 9 months ago
17 Oct 2013
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
fद्वतीय चरण की स्वीकृfत प्राप्त। -- as on 31-Jul-2020
Physical Peramenters