Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.5 | 2.5 | 2.500 | 0 | 0.000 | 0.000 |
67W423 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2003/।।।(2)/16-37(एम0एल0ए0)2015 दि0 27.06.2016
TS Amount (lakhs) : 299.27 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
299.27
Resanction Cost :
299.27
Tentative Cost :
299.27
Exp. Upto Last Fy : 274.54
For CFY 2024-2025
Remaining : 24.73
Demand : 24.50
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 274.54
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
8 years 2 weeks ago
27 Jun 2016
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्य शेष। -- as on 06-Apr-2024
Physical Peramenters