Work Profile

67W429 :

No Pic Avilable Time series Gantt
चमधार-सिरौ-नउकोटी-खोगसा-तीर-महड-साकनीखेत मोटर मार्ग का नव निर्माण कार्य।


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : 2014/।।।(2)/16-139(प्रा0आ0)/2011 दि0 30.06.2016

TS Amount (lakhs) : 499.6 Lacs

Financial Detail (in Rs Lakhs)

Sanction Cost :

499.60

Resanction Cost :

499.60

Tentative Cost :

499.60

Exp. Upto Last Fy : 414.74

For CFY 2024-2025

Remaining : 84.86

Demand : 40.00

Allotment : 0.00

Exp in CFY : 0.00

Total Up to Date Exp : 414.74

Construction Started

Physical Progress:

At start of FY 2024-2025 : 90 %

Up to Date : 90 %

Sanction on :
8 years 2 weeks ago
30 Jun 2016


Tentative Completion date:
8 months 1 week from now
31 Mar 2025


Actual Completion Date:
Not Yet Reported


Rating : 107

Remark

Bottelneck: no issue


10 कि0मी0 पहाड कटान का कार्य पूर्ण। 9.50 कि0मी0 पार्ट-2 का कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 21-Apr-2022

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 10 10 9.500 0.5 0.500 0.000
Currently only Bank Gaurantee information is avilable