Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 10 | 10 | 9.500 | 0.5 | 0.500 | 0.000 |
67W429 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2014/।।।(2)/16-139(प्रा0आ0)/2011 दि0 30.06.2016
TS Amount (lakhs) : 499.6 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
499.60
Resanction Cost :
499.60
Tentative Cost :
499.60
Exp. Upto Last Fy : 414.74
For CFY 2024-2025
Remaining : 84.86
Demand : 40.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 414.74
Construction Started
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
8 years 2 weeks ago
30 Jun 2016
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
10 कि0मी0 पहाड कटान का कार्य पूर्ण। 9.50 कि0मी0 पार्ट-2 का कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 21-Apr-2022
Physical Peramenters