Work Profile Report [67W429]

चमधार-सिरौ-नउकोटी-खोगसा-तीर-महड-साकनीखेत मोटर मार्ग का नव निर्माण कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : 2014/।।।(2)/16-139(प्रा0आ0)/2011 दि0 30.06.2016

TS Amount (lakhs) : 499.6 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

499.60

Resanction Cost :

499.60

Tentative Cost :

499.60

Exp. Upto Last Fy :

414.74

For CFY 2024-2025

Remaining :

84.86

Demand :

40.00

Allotment :

0.00

Exp in CFY :

7.33

Total Up to Date Exp :

422.07

Construction Started

Sanction on : 8 years 4 months ago

30 Jun 2016

Physical Progress:

At start of FY 2024-2025 :

90 %

Up to Date :

90 %

Tentative Completion date on : 4 months 1 week from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
10
10
9.500
0.5
0.500
0.000

Remark

view all

कार्य पूर्ण। दायित्य शेष। -- as on 03-Aug-2024

Rating : 98

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand