Work Profile Report [67W454]
Remarks
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 1058/जि0यो0/लो0नि0वि0/2016-17 दि0 31.08.2016
TS Amount (lakhs) : 24.19 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
24.19
Resanction Cost :
24.19
Tentative Cost :
24.19
Exp. Upto Last Fy :
4.42
For CFY 2024-2025
Remaining :
19.77
Demand :
5.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
4.42
Construction Started
Sanction on : 8 years 2 months ago
31 Aug 2016
Physical Progress:
At start of FY 2024-2025 :
40 %
Up to Date :
40 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 31-Jul-2020
Assets :
Work not linked with IM
Bridges on The Basis of AI: