Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 0 | 1 | 0 | 0 |
67W455 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1058/जि0यो0/लो0नि0वि0/2016-17 दि0 31.08.2016
TS Amount (lakhs) : 35 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
35.00
Resanction Cost :
35.00
Tentative Cost :
35.00
Exp. Upto Last Fy : 9.98
For CFY 2024-2025
Remaining : 25.02
Demand : 5.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 9.98
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 40 %
Sanction on :
7 years 10 months ago
31 Aug 2016
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पगति पर। -- as on 31-Jul-2020
Physical Peramenters