Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 0 | 1 | 0 | 0 |
67W455 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1058/जि0यो0/लो0नि0वि0/2016-17 दि0 31.08.2016
TS Amount (lakhs) : 35 Lacs
Financial Detail
Sanction Cost : 35.00 Lacs
Resanction Cost : 35.00 Lacs
Exp. Upto Last Fy : 9.98 Lacs
For CFY 2024-2025
Remaining : 25.02 Lacs
Demand : 5.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 9.98 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 40 %
Sanction on :
7 years 8 months ago
31 Aug 2016
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पगति पर। -- as on 31-Jul-2020
Physical Peramenters