Work Profile Report [67W464]

पौड़ी-ल्वाली मोटर मार्ग से ग्राम ननकोट के लिए सम्पर्क मोटर मार्ग का नव निर्माण कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : 3042/।।।(2)/16-65(्रप्र्रा0आ0)/2007 दि0 23.11.2016

TS Amount (lakhs) : 120.9 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

120.90

Resanction Cost :

120.90

Tentative Cost :

120.90

Exp. Upto Last Fy :

97.81

For CFY 2024-2025

Remaining :

23.09

Demand :

20.00

Allotment :

10.61

Exp in CFY :

10.61

Total Up to Date Exp :

108.42

Construction Started

Sanction on : 8 years 15 hours ago

23 Nov 2016

Physical Progress:

At start of FY 2024-2025 :

90 %

Up to Date :

90 %

Tentative Completion date on : 1 year 1 month from now

31 Dec 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
2
2
0.000
2
0.000
0.000

Remark

view all

कार्य प्रगति पर। -- as on 05-Feb-2024

Rating : 119

Forest Case Pending At : 21: Final

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand