Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 4.000 | 0 | 0.000 | 0.000 |
67W471 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2201/।।।(2)/17-37/(एम0एल0ए0)/2017 टी0सी0 1 दि0 12.09.2017
TS Amount (lakhs) : 267.4 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
267.40
Resanction Cost :
267.40
Tentative Cost :
267.40
Exp. Upto Last Fy : 249.81
For CFY 2024-2025
Remaining : 17.59
Demand : 17.00
Allotment : 3.00
Exp in CFY : 2.51
Total Up to Date Exp : 252.32
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
6 years 10 months ago
12 Sep 2017
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्य शेष। -- as on 30-Apr-2021
Physical Peramenters