Work Profile Report [67W525]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 8111/।।।(2)/18-37(एम0एल0ए0)/2017 दि0 28.12.2018
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
153.65
Resanction Cost :
153.65
Tentative Cost :
153.65
Exp. Upto Last Fy :
3.28
For CFY 2024-2025
Remaining :
150.37
Demand :
13.00
Allotment :
21.16
Exp in CFY :
21.76
Total Up to Date Exp :
25.03
Phase1 DPR Submitted
Sanction on : 5 years 10 months ago
28 Dec 2018
Physical Progress:
At start of FY 2024-2025 :
10 %
Up to Date :
10 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
द्वितीय चरण की स्वीकृति प्राप्त प्रतिकर भुगतान की कार्यवाही की जा रही है। -- as on 10-Jan-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand