Work Profile Report [67W534]

सुतारगांव-छवढेकरी मोटर मार्ग का काण्डई तक विस्तार का कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : 566/।।।(2)/19-37(एम0एल0ए0)/2017टी0सी0 दि0 04.02.2019

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

56.61

Resanction Cost :

56.61

Tentative Cost :

56.61

Exp. Upto Last Fy :

0.87

For CFY 2024-2025

Remaining :

55.74

Demand :

5.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.87

Phase1 DPR Submitted

Sanction on : 5 years 10 months ago

04 Feb 2019

Physical Progress:

At start of FY 2024-2025 :

0 %

Up to Date :

0 %

Tentative Completion date on : 3 months 6 days from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
3
3
0.000
3
0.000
0.000

Remark

view all

सर्वेक्षण कार्य एवं समरेखण कार्य पूर्ण। डी0पी0आर0 प्रेषित कास्तकारों से सम्पर्क कर मुआवजा वितरण की कार्यवाही गतिमान, मार्च 2025 तक मुआवजा वितरण कर दिया जायेगा। (द्वितीय चरण का कार्य स्वीकृत वर्तमन में मार्ग यातायात के लिए सुलभ है। -- as on 07-Aug-2024

Rating : 2

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: