Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.75 | 4.75 | 4.750 | 0 | 0.000 | 0.000 |
67W537 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 410/।।।(2)/19-37(एम0एल0ए0)/2017 दि0 29.01.2019
TS Amount (lakhs) : 231.26 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
231.26
Resanction Cost :
231.26
Tentative Cost :
231.26
Exp. Upto Last Fy : 198.98
For CFY 2024-2025
Remaining : 32.28
Demand : 30.00
Allotment : 10.00
Exp in CFY : 10.18
Total Up to Date Exp : 209.16
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
5 years 5 months ago
29 Jan 2019
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्णं। दायित्य शेष। -- as on 21-Apr-2022
Physical Peramenters