Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.5 | 3.5 | 3.350 | 0.15 | 0.000 | 0.000 |
67W562 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 512/।।।(2)/20-37(एम0एल0ए0)/2017टी0सी0-1 दि0 03.02.2020
TS Amount (lakhs) : 174.37 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
174.37
Resanction Cost :
174.37
Tentative Cost :
174.37
Exp. Upto Last Fy : 152.59
For CFY 2024-2025
Remaining : 21.78
Demand : 21.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 152.59
Work completed
Physical Progress:
At start of FY 2024-2025 : 95 %
Up to Date : 95 %
Sanction on :
4 years 5 months ago
03 Feb 2020
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्य शेष। -- as on 12-Apr-2024
Physical Peramenters