Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 0.000 | 4 | 0.000 | 0.000 |
67W596 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1025/।।।(2)/250-11(प्रा0आ0)/2017 दि0 19.06.2020
TS Amount (lakhs) : 264.74 Lacs
Financial Detail
Sanction Cost : 264.74 Lacs
Resanction Cost : 264.74 Lacs
Exp. Upto Last Fy : 247.76 Lacs
For CFY 2024-2025
Remaining : 16.98 Lacs
Demand : 16.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 247.76 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 11 months ago
19 Jun 2020
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्य शेष। -- as on 12-Apr-2024
Physical Peramenters