Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 0.000 | 4 | 0.000 | 0.000 |
67W596 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1025/।।।(2)/250-11(प्रा0आ0)/2017 दि0 19.06.2020
TS Amount (lakhs) : 264.74 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
264.74
Resanction Cost :
264.74
Tentative Cost :
264.74
Exp. Upto Last Fy : 247.76
For CFY 2024-2025
Remaining : 16.98
Demand : 16.00
Allotment : 10.00
Exp in CFY : 0.02
Total Up to Date Exp : 247.78
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
4 years 4 weeks ago
19 Jun 2020
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्य शेष। -- as on 12-Apr-2024
Physical Peramenters