Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 2.500 | 0.5 | 0.000 | 0.000 |
67W624 :
Administrative Approval Detail : 1389/।।।(2)/21-37(एम0एल0ए0)2017 टी0सी0-2 दि0 21.05.2021
TS Amount (lakhs) : 77.3 Lacs
Financial Detail
Sanction Cost : 77.30 Lacs
Resanction Cost : 77.30 Lacs
Exp. Upto Last Fy : 40.59 Lacs
For CFY 2024-2025
Remaining : 36.71 Lacs
Demand : 30.00 Lacs
Allotment : 20.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 40.59 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 11 months ago
21 May 2021
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्य शेष। -- as on 06-Apr-2024
Physical Peramenters