Work Profile Report [67W625]

नवन पल्ला से पथराडाखाल-गैठीछेडा मोटर मार्ग पर जोडने हेतु मोटर मार्ग का निर्माण कार्य। (द्वितीय चरण स्टेज-1)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : 1389/।।।(2)/21-37(एम0एल0ए0)/2017टी0सी0-2 दि0 21.05.2021

TS Amount (lakhs) : 49.32 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

49.32

Resanction Cost :

49.32

Tentative Cost :

49.32

Exp. Upto Last Fy :

44.17

For CFY 2024-2025

Remaining :

5.15

Demand :

5.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

44.17

Work completed

Sanction on : 3 years 6 months ago

21 May 2021

Physical Progress:

At start of FY 2024-2025 :

100 %

Up to Date :

100 %

Tentative Completion date on : 4 months 1 week from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
2
2
2.000
0
0.000
0.000

Remark

view all

कार्य पूर्ण। दायित्य शेष। -- as on 04-Jun-2022

Rating : 122

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: