Work Profile

नवन पल्ला से पथराडाखाल-गैठीछेडा मोटर मार्ग पर जोडने हेतु मोटर मार्ग का निर्माण कार्य। (द्वितीय चरण स्टेज-1)


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : 1389/।।।(2)/21-37(एम0एल0ए0)/2017टी0सी0-2 दि0 21.05.2021

TS Amount (lakhs) : 49.32 Lacs

Financial Detail

Sanction Cost : 49.32 Lacs

Resanction Cost : 49.32 Lacs

Exp. Upto Last Fy : 44.17 Lacs

For CFY 2024-2025

Remaining : 5.15 Lacs

Demand : 5.00 Lacs

Allotment : 0.00 Lacs

Exp in CFY : 0.00 Lacs

Total Up to Date Exp : 44.17 Lacs

Work completed

Physical Progress:

At start of FY 2024-2025 : 100 %

Up to Date : 100 %

Sanction on :
2 years 11 months ago
21 May 2021


Tentative Completion date:
10 months 1 week from now
31 Mar 2025


Actual Completion Date:
Not Yet Reported


Rating : 167

Remark

Bottelneck: no issue


कार्य पूर्ण। दायित्य शेष। -- as on 04-Jun-2022

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 2 2 2.000 0 0.000 0.000
Currently only Bank Gaurantee information is avilable