Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2.000 | 0 | 0.000 | 0.000 |
67W625 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1389/।।।(2)/21-37(एम0एल0ए0)/2017टी0सी0-2 दि0 21.05.2021
TS Amount (lakhs) : 49.32 Lacs
Financial Detail
Sanction Cost : 49.32 Lacs
Resanction Cost : 49.32 Lacs
Exp. Upto Last Fy : 44.17 Lacs
For CFY 2024-2025
Remaining : 5.15 Lacs
Demand : 5.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 44.17 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 11 months ago
21 May 2021
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्य शेष। -- as on 04-Jun-2022
Physical Peramenters