Work Profile Report [67W627]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 2313/।।।(2)/21-01(प्रा0आ0)2021 दि0 23.07.2021
TS Amount (lakhs) : 43.12 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
43.12
Resanction Cost :
43.12
Tentative Cost :
43.12
Exp. Upto Last Fy :
38.77
For CFY 2024-2025
Remaining :
4.35
Demand :
4.00
Allotment :
0.00
Exp in CFY :
3.73
Total Up to Date Exp :
42.51
Work completed
Sanction on : 3 years 4 months ago
23 Jul 2021
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्य शेष। -- as on 17-Apr-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand