Work Profile

तैडी-विजयनगर-मरोडा मोटर मार्ग का नव निर्माण कार्य। (द्वितीय चरण स्टेज-। )


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : 1706/।।।(2)/21-37(एम0एल0ए0)2017टी0सी0-1 दि0 17.06.2021

TS Amount (lakhs) : 92.11 Lacs

Financial Detail

Sanction Cost : 92.11 Lacs

Resanction Cost : 92.11 Lacs

Exp. Upto Last Fy : 69.24 Lacs

For CFY 2024-2025

Remaining : 22.87 Lacs

Demand : 15.00 Lacs

Allotment : 0.00 Lacs

Exp in CFY : 0.00 Lacs

Total Up to Date Exp : 69.24 Lacs

Construction Started

Physical Progress:

At start of FY 2024-2025 : 80 %

Up to Date : 80 %

Sanction on :
2 years 11 months ago
17 Jun 2021


Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024


Actual Completion Date:
Not Yet Reported


Rating : 80

Remark

Bottelneck: no issue


3.50 कि0मी0 पहाड कटान का कार्य पूर्ण। -- as on 12-Apr-2024

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 4 4 2.500 1.5 0.000 0.000
Jobs 4 4 0 4 0 0
Currently only Bank Gaurantee information is avilable