Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.5 | 2.5 | 2.500 | 0 | 0.000 | 0.000 |
Jobs | 3 | 3 | 0 | 3 | 0 | 0 |
67W650 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 3193(1)/।।।(2)/20-06(मु0मं0घो0)/2015 दि0 26.08.2021
TS Amount (lakhs) : 71.4 Lacs
Financial Detail
Sanction Cost : 71.40 Lacs
Resanction Cost : 71.40 Lacs
Exp. Upto Last Fy : 44.70 Lacs
For CFY 2024-2025
Remaining : 26.70 Lacs
Demand : 26.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 44.70 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 8 months ago
26 Aug 2021
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्य शेष। -- as on 17-Apr-2023
Physical Peramenters