Work Profile Report [67W651]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 3244(1)/।।।(2)/21-37(एम0एल0ए0)2017 टी0सी0-2 दिनांक 01.09.2021
TS Amount (lakhs) : 34.51 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
34.51
Resanction Cost :
34.51
Tentative Cost :
34.51
Exp. Upto Last Fy :
31.06
For CFY 2024-2025
Remaining :
3.45
Demand :
3.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
31.06
Work completed
Sanction on : 3 years 3 months ago
01 Sep 2021
Physical Progress:
At start of FY 2024-2025 :
95 %
Up to Date :
95 %
Tentative Completion date on : 3 months 6 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्य शेष। -- as on 17-Apr-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI: