Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2.000 | 0 | 0.000 | 0.000 |
Jobs | 2 | 2 | 0 | 2 | 0 | 0 |
67W661 :
Administrative Approval Detail : 3331(1)/।।।(2)/21-01(प्रा0आ0)2021 दि0, 03.09.2021
TS Amount (lakhs) : 43.82 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
43.82
Resanction Cost :
43.82
Tentative Cost :
43.82
Exp. Upto Last Fy : 36.31
For CFY 2024-2025
Remaining : 7.51
Demand : 7.50
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 36.31
Work completed
Physical Progress:
At start of FY 2024-2025 : 95 %
Up to Date : 95 %
Sanction on :
2 years 10 months ago
03 Sep 2021
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्य शेष। -- as on 12-Apr-2024
Physical Peramenters