Work Profile

एन0एच0-119 से चन्दोला राई तक मोटर मार्ग का नव निर्माण कार्य। (द्वितीय चरण स्टेज-।)


Work not linked with IM

Roads on The Basis of AI: Road 1

Bridges on The Basis of AI: arch bridge

Administrative Approval Detail : 3331(1)/।।।(2)/21-01(प्रा0आ0)2021 दि0, 03.09.2021

TS Amount (lakhs) : 43.82 Lacs

Financial Detail

Sanction Cost : 43.82 Lacs

Resanction Cost : 43.82 Lacs

Exp. Upto Last Fy : 36.31 Lacs

For CFY 2024-2025

Remaining : 7.51 Lacs

Demand : 7.50 Lacs

Allotment : 0.00 Lacs

Exp in CFY : 0.00 Lacs

Total Up to Date Exp : 36.31 Lacs

Work completed

Physical Progress:

At start of FY 2024-2025 : 95 %

Up to Date : 95 %

Sanction on :
2 years 8 months ago
03 Sep 2021


Tentative Completion date:
10 months 1 week from now
31 Mar 2025


Actual Completion Date:
Not Yet Reported


Rating : 165

Remark

Bottelneck: no issue


कार्य पूर्ण। दायित्य शेष। -- as on 12-Apr-2024

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 2 2 2.000 0 0.000 0.000
Jobs 2 2 0 2 0 0
Currently only Bank Gaurantee information is avilable