Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.5 | 1.5 | 1.500 | 0 | 0.000 | 0.000 |
Jobs | 2 | 2 | 0 | 2 | 0 | 0 |
67W663 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 6029/।।।(2)/21-37(एम0एल0ए0)2017 दि0 14.12.2021
TS Amount (lakhs) : 36.61 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
36.61
Resanction Cost :
36.61
Tentative Cost :
36.61
Exp. Upto Last Fy : 23.55
For CFY 2024-2025
Remaining : 13.06
Demand : 13.00
Allotment : 0.00
Exp in CFY : 8.14
Total Up to Date Exp : 31.68
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 7 months ago
14 Dec 2021
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्य शेष। -- as on 12-Apr-2024
Physical Peramenters