Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 1.500 | 1.5 | 0.000 | 0.000 |
Jobs | 3 | 3 | 0 | 3 | 0 | 0 |
67W672 :
Administrative Approval Detail : 466(1)/।।।(2)/22-71(प्रा0आ0)2013 दि0 07.01.2022
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
107.09
Resanction Cost :
107.09
Tentative Cost :
107.09
Exp. Upto Last Fy : 93.34
For CFY 2024-2025
Remaining : 13.75
Demand : 10.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 93.34
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 6 months ago
07 Jan 2022
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्य शेष। -- as on 12-Apr-2024
Physical Peramenters