Work Profile Report [67W672]

बड़खोलू रौतेला काण्डा मोटर मार्ग के कि0मी0 6 से कुड़िगांव-हैडाखोली मोटर मार्ग का नवनिर्माण कार्य। (द्वितीय चरण स्टेज-। )
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : 466(1)/।।।(2)/22-71(प्रा0आ0)2013 दि0 07.01.2022

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

107.09

Resanction Cost :

107.09

Tentative Cost :

107.09

Exp. Upto Last Fy :

93.34

For CFY 2024-2025

Remaining :

13.75

Demand :

10.00

Allotment :

5.00

Exp in CFY :

4.69

Total Up to Date Exp :

98.02

Work completed

Sanction on : 2 years 10 months ago

07 Jan 2022

Physical Progress:

At start of FY 2024-2025 :

100 %

Up to Date :

100 %

Tentative Completion date on : 4 months 1 week from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
3
3
1.500
1.5
0.000
0.000
Jobs
3
3
0
3
0
0

Remark

view all

कार्य पूर्ण। दायित्य शेष। -- as on 12-Apr-2024

Rating : 128

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Roads on The Basis of AI: Road 1

Bridges on The Basis of AI: