Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 2.500 | 0.000 |
Jobs | 5 | 5 | 0 | 5 | 0 | 0 |
67W696 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : लोक निर्माण अनुभाग-2 दि0 19.10.2022
TS Amount (lakhs) : 155.54 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
155.54
Resanction Cost :
155.54
Tentative Cost :
155.54
Exp. Upto Last Fy : 13.69
For CFY 2024-2025
Remaining : 141.85
Demand : 30.00
Allotment : 5.00
Exp in CFY : 0.14
Total Up to Date Exp : 13.83
Construction Started
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 30 %
Sanction on :
1 year 9 months ago
10 Oct 2022
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 03-Jul-2023
Physical Peramenters