Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6.73 | 6.73 | 0.000 | 6.73 | 6.730 | 6.730 |
Jobs | 1 | 1 | 0 | 1 | 0 | 0 |
67W709 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 895/07याताा0-पी0एम0जी0एस0वाई0-नि0।।। दि0 16.05.2023
TS Amount (lakhs) : 117.7 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
117.72
Resanction Cost :
117.72
Tentative Cost :
117.72
Exp. Upto Last Fy : 16.44
For CFY 2024-2025
Remaining : 101.28
Demand : 101.28
Allotment : 30.51
Exp in CFY : 30.51
Total Up to Date Exp : 46.95
Work completed
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 100 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
2 months 2 weeks ago
30 Apr 2024
Actual Completion Date:
2 months 2 weeks ago
30 Apr 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्य शेष। -- as on 07-Jun-2024
Physical Peramenters