Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 53 | 53 | 0.000 | 53 | 0.000 | 0.000 |
Jobs | 1 | 1 | 0 | 1 | 0 | 0 |
67W741 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 9451/।।।(2)/23-01(प्रा0आ0)/2019 दि0 21.07.2023
TS Amount (lakhs) : 570.28 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
570.28
Resanction Cost :
570.28
Tentative Cost :
570.28
Exp. Upto Last Fy : 384.98
For CFY 2024-2025
Remaining : 185.30
Demand : 185.30
Allotment : 70.00
Exp in CFY : 118.90
Total Up to Date Exp : 503.88
Work completed
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 100 %
Sanction on :
11 months 3 weeks ago
21 Jul 2023
Tentative Completion date:
4 months 2 weeks ago
28 Feb 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्य शेष। -- as on 07-Jun-2024
Physical Peramenters