Work Profile

टिहरी-हिण्डोलाखाल-देवप्रयाग-व्यासघाट-बिलखेत (एस0एच0-49) ल0 31.50 कि0मी0 । अदवानी-नाहसैण-सुरपुर-बहेडाखाल-खाण्डा मोटर मार्ग ल0 36.50 कि0मी0 । (अन्य जिला मार्ग)


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : 9451/।।।(2)/23-01(प्रा0आ0)/2019 दि0 21.07.2023

TS Amount (lakhs) : 570.28 Lacs

Financial Detail (in Rs Lakhs)

Sanction Cost :

570.28

Resanction Cost :

570.28

Tentative Cost :

570.28

Exp. Upto Last Fy : 384.98

For CFY 2024-2025

Remaining : 185.30

Demand : 185.30

Allotment : 70.00

Exp in CFY : 118.90

Total Up to Date Exp : 503.88

Work completed

Physical Progress:

At start of FY 2024-2025 : 80 %

Up to Date : 100 %

Sanction on :
11 months 3 weeks ago
21 Jul 2023


Tentative Completion date:
4 months 2 weeks ago
28 Feb 2024


Actual Completion Date:
Not Yet Reported


Rating : 100

Remark

Bottelneck: no issue


कार्य पूर्ण। दायित्य शेष। -- as on 07-Jun-2024

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 53 53 0.000 53 0.000 0.000
Jobs 1 1 0 1 0 0
Currently only Bank Gaurantee information is avilable