Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 0.000 | 2 | 2.000 | 0.000 |
Jobs | 1 | 1 | 0 | 1 | 0 | 0 |
67W744 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : लोक निर्माण अनुभाग-2 ई पत्रावली संख्या- 37510 दि0 22.08.2023
TS Amount (lakhs) : 145.77 Lacs
Financial Detail
Sanction Cost : 145.77 Lacs
Resanction Cost : 145.77 Lacs
Exp. Upto Last Fy : 0.10 Lacs
For CFY 2024-2025
Remaining : 145.67 Lacs
Demand : 100.00 Lacs
Allotment : 50.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.10 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 30 %
Sanction on :
8 months 3 weeks ago
22 Aug 2023
Tentative Completion date:
4 weeks 1 day ago
20 Apr 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 15-Dec-2023
Physical Peramenters