Work Profile

बनेख से बलूनी मोटर मार्ग का पक्कीकरण व डामरीकरण का कार्य।


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : लोक निर्माण अनुभाग-2 ई पत्रावली संख्या- 37510 दि0 22.08.2023

TS Amount (lakhs) : 145.77 Lacs

Financial Detail (in Rs Lakhs)

Sanction Cost :

145.77

Resanction Cost :

145.77

Tentative Cost :

145.77

Exp. Upto Last Fy : 0.10

For CFY 2024-2025

Remaining : 145.67

Demand : 100.00

Allotment : 47.94

Exp in CFY : 47.94

Total Up to Date Exp : 48.04

Work completed

Physical Progress:

At start of FY 2024-2025 : 30 %

Up to Date : 95 %

Sanction on :
10 months 3 weeks ago
22 Aug 2023


Tentative Completion date:
2 weeks 3 days ago
30 Jun 2024


Actual Completion Date:
Not Yet Reported


Rating : 95

Remark

Bottelneck: no issue


कार्य प्रगति पर। -- as on 26-Jun-2024

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 2 2 0.000 2 2.000 2.000
Jobs 1 1 0 1 0 0
Currently only Bank Gaurantee information is avilable