Work Profile Report [67W745]

चिलोली-किमोली मोटर मार्ग का पक्कीकरण व डामरीकरण का कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Nabard
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : लोक निर्माण अनुभाग-2 ई पत्रावली सं0 26412 दि0 09.10.2023

TS Amount (lakhs) : 244.31 Lacs

Budget Financial Head : NABARD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

244.31

Resanction Cost :

244.31

Tentative Cost :

244.31

Exp. Upto Last Fy :

112.57

For CFY 2025-2026

Remaining :

131.74

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

112.57

Construction Started

Sanction on : 1 year 5 months ago

09 Oct 2023

Physical Progress:

At start of FY 2025-2026 :

20 %

Up to Date :

75 %

Tentative Completion date on : 2 months 1 day ago

04 Feb 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
3.65
3.65
0.000
3.65
3.650
0.000
Jobs
1
1
0
1
0
0

Remark

view all

जी0-1, जी-2 जी-3 का कार्य पूर्ण। पी0सी0 का कार्य प्रगति पर। -- as on 02-Apr-2025

Rating : 75

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: