Work Profile Report [67W745]
Remarks
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : लोक निर्माण अनुभाग-2 ई पत्रावली सं0 26412 दि0 09.10.2023
TS Amount (lakhs) : 244.31 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
244.31
Resanction Cost :
244.31
Tentative Cost :
244.31
Exp. Upto Last Fy :
0.35
For CFY 2024-2025
Remaining :
243.96
Demand :
63.64
Allotment :
65.87
Exp in CFY :
65.87
Total Up to Date Exp :
66.22
Construction Started
Sanction on : 1 year 1 month ago
09 Oct 2023
Physical Progress:
At start of FY 2024-2025 :
20 %
Up to Date :
40 %
Tentative Completion date on : 2 months 1 week from now
04 Feb 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 02-Jan-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand