Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.65 | 3.65 | 0.000 | 3.65 | 3.650 | 0.000 |
Jobs | 1 | 1 | 0 | 1 | 0 | 0 |
67W745 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : लोक निर्माण अनुभाग-2 ई पत्रावली सं0 26412 दि0 09.10.2023
TS Amount (lakhs) : 244.31 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
244.31
Resanction Cost :
244.31
Tentative Cost :
244.31
Exp. Upto Last Fy : 0.35
For CFY 2024-2025
Remaining : 243.96
Demand : 128.00
Allotment : 33.63
Exp in CFY : 24.09
Total Up to Date Exp : 24.44
Construction Started
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 40 %
Sanction on :
9 months 1 week ago
09 Oct 2023
Tentative Completion date:
6 months 2 weeks from now
04 Feb 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 02-Jan-2024
Physical Peramenters