Work Profile

चिलोली-किमोली मोटर मार्ग का पक्कीकरण व डामरीकरण का कार्य।


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : लोक निर्माण अनुभाग-2 ई पत्रावली सं0 26412 दि0 09.10.2023

TS Amount (lakhs) : 244.31 Lacs

Financial Detail

Sanction Cost : 244.31 Lacs

Resanction Cost : 244.31 Lacs

Exp. Upto Last Fy : 0.35 Lacs

For CFY 2024-2025

Remaining : 243.96 Lacs

Demand : 128.00 Lacs

Allotment : 50.00 Lacs

Exp in CFY : 0.00 Lacs

Total Up to Date Exp : 0.35 Lacs

Construction Started

Physical Progress:

At start of FY 2024-2025 : 20 %

Up to Date : 20 %

Sanction on :
7 months 1 week ago
09 Oct 2023


Tentative Completion date:
8 months 2 weeks from now
04 Feb 2025


Actual Completion Date:
Not Yet Reported


Rating : 75

Remark

Bottelneck: no issue


कार्य प्रगति पर। -- as on 02-Jan-2024

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 3.65 3.65 0.000 3.65 3.650 0.000
Jobs 1 1 0 1 0 0
Currently only Bank Gaurantee information is avilable