Work Profile Report [67W745]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : लोक निर्माण अनुभाग-2 ई पत्रावली सं0 26412 दि0 09.10.2023
TS Amount (lakhs) : 244.31 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
244.31
Resanction Cost :
244.31
Tentative Cost :
244.31
Exp. Upto Last Fy :
112.57
For CFY 2025-2026
Remaining :
131.74
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
112.57
Construction Started
Sanction on : 1 year 5 months ago
09 Oct 2023
Physical Progress:
At start of FY 2025-2026 :
20 %
Up to Date :
75 %
Tentative Completion date on : 2 months 1 day ago
04 Feb 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
जी0-1, जी-2 जी-3 का कार्य पूर्ण। पी0सी0 का कार्य प्रगति पर। -- as on 02-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: