Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 5.000 | 4.000 |
Jobs | 1 | 1 | 0 | 1 | 0 | 0 |
67W746 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : लोक निर्माण अनुभाग-2 ई पत्रावली सं0- 37510 दि0 12.10.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
172.27
Resanction Cost :
172.27
Tentative Cost :
172.27
Exp. Upto Last Fy : 27.09
For CFY 2024-2025
Remaining : 145.18
Demand : 50.00
Allotment : 35.00
Exp in CFY : 30.81
Total Up to Date Exp : 57.90
Construction Started
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 60 %
Sanction on :
9 months 5 days ago
12 Oct 2023
Tentative Completion date:
4 months 2 weeks ago
28 Feb 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 05-Feb-2024
Physical Peramenters