Work Profile

कोठी-धारी-पोखरी-ली तक मोटर मार्ग का नव निर्माण कार्य। (द्वितीय चरण स्टेज-।)


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : लोक निर्माण अनुभाग-2 ई पत्रावली सं0- 37510 दि0 12.10.2023

TS Amount (lakhs) : 0 Lacs

Financial Detail (in Rs Lakhs)

Sanction Cost :

172.27

Resanction Cost :

172.27

Tentative Cost :

172.27

Exp. Upto Last Fy : 27.09

For CFY 2024-2025

Remaining : 145.18

Demand : 50.00

Allotment : 35.00

Exp in CFY : 30.81

Total Up to Date Exp : 57.90

Construction Started

Physical Progress:

At start of FY 2024-2025 : 30 %

Up to Date : 60 %

Sanction on :
9 months 5 days ago
12 Oct 2023


Tentative Completion date:
4 months 2 weeks ago
28 Feb 2024


Actual Completion Date:
Not Yet Reported


Rating : 60

Remark

Bottelneck: no issue


कार्य प्रगति पर। -- as on 05-Feb-2024

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 5 5 0.000 5 5.000 4.000
Jobs 1 1 0 1 0 0
Currently only Bank Gaurantee information is avilable