Work Profile Report [67W753]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : लोक निर्माण अनुभाग-2 ई0 पत्रावली सं0 48456 दि0 23.02.2024
TS Amount (lakhs) : 198.36 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
198.36
Resanction Cost :
198.36
Tentative Cost :
198.36
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
198.36
Demand :
100.00
Allotment :
0.31
Exp in CFY :
0.31
Total Up to Date Exp :
0.31
Construction Started
Sanction on : 9 months 16 hours ago
23 Feb 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
10 %
Tentative Completion date on : 1 month 1 week from now
31 Dec 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
सिविल कार्य प्रगति पर। क्षतिग्रस्त दीवारों का निर्माण कार्य किया जा रहा है। -- as on 29-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand