Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7.95 | 7.95 | 0.000 | 7.95 | 7.950 | 0.000 |
Jobs | 1 | 1 | 0 | 1 | 0 | 0 |
67W755 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : लोक निर्माण अनुभाग-2 ई0 पत्रावली सं0 48456 दि0 23.02.2024
TS Amount (lakhs) : 150.41 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
150.41
Resanction Cost :
150.41
Tentative Cost :
150.41
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 150.41
Demand : 100.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 30 %
Sanction on :
4 months 3 weeks ago
23 Feb 2024
Tentative Completion date:
1 month 3 weeks from now
13 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 15-Jun-2024
Physical Peramenters