Work Profile Report [67W756]
Remarks
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : लोक निर्माण अनुभाग-2 ई0 पत्रावली सं0 36342 दि0 22.02.2024
TS Amount (lakhs) : 219.61 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
219.61
Resanction Cost :
219.61
Tentative Cost :
219.61
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
219.61
Demand :
155.00
Allotment :
100.00
Exp in CFY :
20.06
Total Up to Date Exp :
20.06
Construction Started
Sanction on : 10 months 3 days ago
22 Feb 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
20 %
Tentative Completion date on : 2 months 2 weeks from now
14 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 06-Apr-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand