Work Profile

बेताल-बौसाल-मुण्डेश्वर-कल्जीखाल मोटर मार्ग।


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : 191/14याता0(क)-उ0/2023 दि0 09.02.2024

TS Amount (lakhs) : 0 Lacs

Financial Detail

Sanction Cost : 80.36 Lacs

Resanction Cost : 80.36 Lacs

Exp. Upto Last Fy : 0.00 Lacs

For CFY 2024-2025

Remaining : 80.36 Lacs

Demand : 80.36 Lacs

Allotment : 50.00 Lacs

Exp in CFY : 0.00 Lacs

Total Up to Date Exp : 0.00 Lacs

Construction Started

Physical Progress:

At start of FY 2024-2025 : 0 %

Up to Date : 0 %

Sanction on :
3 months 1 week ago
09 Feb 2024


Tentative Completion date:
10 months 1 week from now
31 Mar 2025


Actual Completion Date:
Not Yet Reported


Rating : 0

Remark

Bottelneck: no issue


कार्य प्रगति पर। -- as on 01-May-2024

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 5.36 5.36 0.000 5.36 5.360 0.000
Jobs 1 1 0 1 0 0
Currently only Bank Gaurantee information is avilable