Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5.36 | 5.36 | 0.000 | 5.36 | 5.360 | 5.360 |
Jobs | 1 | 1 | 0 | 1 | 0 | 0 |
67W759 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 191/14याता0(क)-उ0/2023 दि0 09.02.2024
TS Amount (lakhs) : 80.36 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
80.36
Resanction Cost :
80.36
Tentative Cost :
80.36
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 80.36
Demand : 80.36
Allotment : 50.00
Exp in CFY : 88.88
Total Up to Date Exp : 88.88
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
5 months 1 week ago
09 Feb 2024
Tentative Completion date:
10 months 4 weeks from now
15 Jun 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायितय शेष। -- as on 26-Jun-2024