Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6.43 | 6.43 | 0.000 | 6.43 | 6.430 | 6.430 |
Jobs | 1 | 1 | 0 | 1 | 0 | 0 |
67W760 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 191/14याता0(क)-उ0/2023 दि0 09.02.2024
TS Amount (lakhs) : 96.43 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
96.43
Resanction Cost :
96.43
Tentative Cost :
96.43
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 96.43
Demand : 96.43
Allotment : 50.00
Exp in CFY : 37.82
Total Up to Date Exp : 37.82
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
5 months 1 week ago
09 Feb 2024
Tentative Completion date:
3 weeks 6 days ago
20 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्य शेष। -- as on 07-Jun-2024
Physical Peramenters