Work Profile Report [67W769]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 388/14याता0(क)-उ0/2023 दि0 15.03.2024
TS Amount (lakhs) : 64.2 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
64.20
Resanction Cost :
64.20
Tentative Cost :
64.20
Exp. Upto Last Fy :
64.14
For CFY 2025-2026
Remaining :
0.06
Demand :
0.00
Allotment :
64.14
Exp in CFY :
0.00
Total Up to Date Exp :
64.14
Work completed
Sanction on : 1 year 3 months ago
15 Mar 2024
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
100 %
Tentative Completion date on : 1 month 4 weeks from now
01 Sep 2025
Actual Completion Date : 3 months 1 day ago
31 Mar 2025
Physical Linear Components
Remark
कार्य पूर्णं दायित्य शेष। -- as on 24-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: