Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.28 | 4.28 | 0.000 | 4.28 | 4.280 | 0.000 |
Jobs | 1 | 1 | 0 | 1 | 0 | 0 |
67W777 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 388/14याता0(क)-उ0/2023 दि0 15.03.2024
TS Amount (lakhs) : 64.33 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
64.33
Resanction Cost :
64.33
Tentative Cost :
64.33
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 64.33
Demand : 64.33
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
none
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
4 months 2 days ago
15 Mar 2024
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
चुुनाव आयोग की अनुमति के उपरान्त दि0 09.05.2024 को निविदा आंमत्रित की गई। प्रथम एवं द्वितीय कोई निविदा प्राप्त नही हुई एवं तीसरी बार में दि0 06.06.2024 को प्राप्त हुई है। अनुबन्ध गठन की कार्यवाही गतिमान है। शीध्र कार्य प्रारम्भ कर लिया जायेगा। -- as on 26-Jun-2024
Physical Peramenters