Work Profile Report [67W788]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : लोक निर्माण अनुभाग-2 ई पत्रावली सं0 37890 दि0 19.07.2027
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
161.60
Resanction Cost :
161.60
Tentative Cost :
161.60
Exp. Upto Last Fy :
57.52
For CFY 2025-2026
Remaining :
104.08
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
57.52
Construction Started
Sanction on : 8 months 2 weeks ago
19 Jul 2024
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
50 %
Tentative Completion date on : 4 months 3 weeks from now
28 Aug 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
जी0-1, जी-2 जी-3 का कार्य पूर्ण। पी0सी0 का कार्य हेतु सामग्री एकत्रित की जा रही है। -- as on 02-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand