Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 27 | 15.57 | 6.000 | 9.57 | 2.000 | 0.000 |
68W106 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 1542/111(2)/09-22(मु0म0 धोषणा)/09 दि0 31.03.2010
TS Amount (lakhs) : 895.79 Lacs
Financial Detail
Sanction Cost : 945.00 Lacs
Resanction Cost : 945.00 Lacs
Exp. Upto Last Fy : 712.91 Lacs
For CFY 2024-2025
Remaining : 232.09 Lacs
Demand : 130.00 Lacs
Allotment : 20.00 Lacs
Exp in CFY : 31.54 Lacs
Total Up to Date Exp : 744.45 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
14 years 1 month ago
31 Mar 2010
Tentative Completion date:
3 months 1 week from now
28 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 18: Final Approval
Bottelneck: no issue
किमी0 8 एवं 9 में पार्ट-।। का कार्य प्रगति में है। -- as on 02-May-2024
Physical Peramenters