Work Profile Report [68W111]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शासन के पत्र सं0 ............./।।। (2) / 21 - 39(एम0एल0ए0) 2017 टी0सी0।। दिनंाक 21.05.2021.
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
10.48
Resanction Cost :
10.48
Tentative Cost :
10.48
Exp. Upto Last Fy :
9.30
For CFY 2025-2026
Remaining :
1.18
Demand :
0.00
Allotment :
1.18
Exp in CFY :
0.00
Total Up to Date Exp :
9.30
Construction Started
Sanction on : 4 years 1 month ago
21 May 2021
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
70 %
Tentative Completion date on : 3 months 1 week ago
31 Mar 2025
Actual Completion Date : 3 months 2 weeks ago
26 Mar 2025
Physical Linear Components
Remark
प्रथम चरण की स्वीकृति के सापेक्ष मुआवजा वितरण की कार्यवाही की जा रही है -- as on 09-Sep-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: