Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 10 | 10 | 10 | 0 |
68W162 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 5927/।।।(2)/13-31 (प्रा0आ0)/2013 दिनांक 22 नवम्बर 2013
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
157.50
Resanction Cost :
157.50
Tentative Cost :
157.50
Exp. Upto Last Fy : 59.23
For CFY 2024-2025
Remaining : 98.27
Demand : 5.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 59.23
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
10 years 7 months ago
22 Nov 2013
Tentative Completion date:
1 year 3 months ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
समस्त कास्तकारों को मुआवजा वितरण कर दिया गया है। अवशेष कास्तकारों को मुआवजा हेतु सूचित कर दिया गया है। -- as on 27-Mar-2024
Physical Peramenters