Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 4 | 0 |
68W17 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 0
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 32.18 Lacs
Resanction Cost : 32.18 Lacs
Exp. Upto Last Fy : 5.25 Lacs
For CFY 2024-2025
Remaining : 26.93 Lacs
Demand : 2.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 5.25 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 15 %
Sanction on :
9 years 1 week ago
08 May 2015
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 13: AIP DFO
Bottelneck: no issue
समरेखण अधी0 अभि0 12वॉ वृत्त, लो0नि0वि0 पौडी के पत्र सं0 3441/1108 याता-12/15 दि0 31.07.2015 द्वारा अनुमोदित।
भारत सरकार पर्यावरण एवं जलवायु परिवर्तन मंत्रालय देहरादून के पत्र सं0 8वी0/यू0सी0पी0/06/53/2020/एफ0सी0/2324 दिनंाक 19.02.21 के द्वारा सैद्धान्तिक स्वीकृति प्राप्त हुई है। सैद्धान्तिक स्वीकृति की शर्तों की अनुपालन आख्या इस कार्यालय के पत्र सं0 559/2भू0अ0 दिनांक 05.04.2024 को पूर्ण कर प्रभागीय वनाधिकारी गढ़वाल वन प्रभाग पौड़ी को प्रेषित की जा चुकी है। पुनः विधिवत स्वीकृति हेतु इस कार्यालय के पत्र सं0 440/2भू0अ0 दिनांक 10/04/2024 के द्वारा प्रभागीय वनाधिकारी गढ़वाल वन प्रभाग पौड़ी को विधिवत स्वीकृति हेतु अपने स्तर से अग्रिम कार्यवाही हेतु लिखा गया है।
-- as on 02-May-2024
Physical Peramenters