Work Profile Report : 68W17
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : 0
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
32.18
Resanction Cost :
32.18
Tentative Cost :
32.18
Exp. Upto Last Fy :
22.32
For CFY 2025-2026
Remaining :
9.86
Demand :
9.86
Allotment :
4.53
Exp in CFY :
4.53
Total Up to Date Exp :
26.85
Construction Started
Sanction on : 10 years 8 months ago
08 May 2015
Physical Progress:
At start of FY 2025-2026 :
55 %
Up to Date :
80 %
Tentative Completion date on : 1 month 3 weeks from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
उक्त प्रस्ताव पर विधिवत स्वीकृति प्राप्त हुई है। -- as on 31-Dec-2025