Work Profile Report [68W181]

गवांनी डमूला मोटर मार्ग पर उपटा देवी बैंड से दलगढ़ तक मोटर मार्ग का निर्माण कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan

  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : Desto Letter No. 269/ Varsik Jila Youjna / S P/ 2021-22 Dt. 06 July 2021

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : Deposit ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

8.00

Resanction Cost :

8.00

Tentative Cost :

8.00

Exp. Upto Last Fy :

0.00

For CFY 2025-2026

Remaining :

8.00

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.00

Unstarted Work

Sanction on : 4 years 1 month ago

06 Jul 2021

Physical Progress:

At start of FY 2025-2026 :

1 %

Up to Date :

1 %

Tentative Completion date on : 7 months 4 weeks ago

31 Dec 2024

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
0.5
0.5
0.5
-

Remark

view all

कास्तकारों द्वारा विवाद किया जा रहा है जिसका व्यय परिवर्तन का प्रस्ताव गठित कर जिलाधिकारी पौड़ी को प्रेषित किया गया है। -- as on 28-Sep-2024

Rating : 1

No Forest Case in The Work

Hindrance / Bottleneck : To Cancel

Assets :

Work not linked with IM

Bridges on The Basis of AI: